![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
[Report an error]
[F.A.Q.]
Supreme Court of Vanuatu |
[Recent Decisions] [Noteup] [Download] [Help]
IN
THE SUPREME COURT OF
THE REPUBLIC OF
VANUATU
(Civil Jurisdiction)
Civil Case No. 102 of
2006
BETWEEN:
CLAUDINE GALIBERT
JONES
Claimant
AND:
SAM
NGWELE & JAY NGWELE
Defendant
Coram: Justice C.N. Tuohy
Counsel: Mr. Yawha for
Claimant
Mr. Ngwele in person
Date of Hearing: 27th March 2008
Date of Decision: 21st May 2008
RESERVED JUDGMENT
Introduction
1. This
is a claim against a building contractor by the owner of a house which the
contractor agreed to build. The claimant terminated
the contract prior to
completion of the house and is seeking to recover from the defendants the cost
of completion and liquidated
damages for delay. As well as denying the claim,
the defendants have counterclaimed for the cost of materials purchased for the
house
but not paid
for.
Facts
2. There
was a written building contract between the parties prepared by the architect,
the late Geoff Feast of James Ferrie &
Partners, and signed on 1 March 2005.
Under it the defendants agreed to construct a new residence for the claimant at
Anabrou in
accordance with annexed drawings and specifications for a fixed price
of VT23,967,000.
3. Clause 6 of the General Conditions of Contract
provided that "the Contractor ......
shall.... regularly and diligently proceed with (the works) and shall complete
the same on or before the date
for practical completion stated in the ....
Appendix subject nevertheless to the provisions for extension......" The
date for practical completion in the appendix was 31 August 2005.
4. In
Clause 26, "practical completion" is
defined as bringing the works to a stage of being reasonably fit for use and/or
occupation by the owner. Clause 29 provided for
the architect to grant fair and
reasonable extension of time for completion if the works had in his opinion been
delayed by various
specified events outside the contractor’s
control.
5. Clause 28 provided that if the contractor failed to complete
the works by the date stated in the appendix or within any extended
time granted
under Clause 29, and the Architect certifies accordingly, the contractor should
pay or allow the owner liquidated damages
as provided in the appendix for the
period during which the works remain uncompleted. The appendix provided that
liquidated damages
were to be calculated at 1/2000th of the contract price per
calendar day i.e. VT 11,984 per day.
6. Clause 23 provided that the owner
had the right to determine the employment of the contractor under the contract
if, inter alia,
the contractor failed to proceed with the works with reasonable
diligence and such default continued for 14 days after a notice specifying
the
default. Such determination is without prejudice to any other rights or
remedies.
7. The claimant presented as evidence 4 sworn statements from
herself, Geoff Feast, Antoine Boudier and Nathaniel Bue. The latter
two related
solely to the cost of completion of the house following termination of the
contract. None of the claimant’s witnesses
were called for
cross-examination. The defendants presented as evidence the sworn statement of
Jay Ngwele. He was cross-examined.
In the event there was little real dispute
about the facts.
8. The contract initially progressed well. Mr. Ngwele
annexed a letter to Mr. Feast dated 1 April 2005 (one month after taking
possession
of the site) setting out progress and mentioning that there had been
according to the Meteo 16 rainy working days in March. However
there is no
evidence that this was unusual for Port Vila in March and no evidence that
either then or later the defendants asked
for an extension on the grounds of
"exceptionally inclement weather" (cl
29 (b)).
9. Mr. Feast stated that three quarters of the way through the
contract, it became evident that the defendants were having financial
problems
which led to difficulties with supplies of materials for the job. Suppliers were
refusing to supply or repossessing material
supplied. Mr. Ngwele in his oral
evidence frankly acknowledged that the firm had become over-extended with
commitments also to another
big contract in Santo. He also blamed a delay by the
company supplying sliding windows and door for the house, but the quotation
from
that company is dated 23 August 2005, a week before practical completion
date.
10. In any event, 31 August 2005 came and went. During the course
of the contract, extras were agreed in the sum of VT925,500. On
19 September
2005, Mr. Feast issued an Interim Certificate No. 7 showing the gross value of
work completed inclusive of extras at
VT 22,166,665. Less retentions of
VT1,200,000, there was an amount due for payment of VT 2m. After that, the
claimant paid a further
VT 2,272,402 in payments direct to suppliers, making a
total paid to or for the account of the defendants of VT23,239,067. I am
satisfied
from the letters produced during the hearing, that the defendants
authorized the payments on their account. The difference between
the total
contract price, inclusive of agreed extras, and the amount actually paid by the
claimant on account of it is VT1,680,433.
11. The evidence is unclear as
to what work was actually carried out on the site after September 2005 but it
seems that the defendants
had ceased to work at the site altogether by about the
start of 2006. There is no real explanation in the evidence as to why. However
the evidence of the considerable amount of work outstanding at the date of
termination and of the cost of that work confirms that
the defendants had
underquoted and were unable to meet the necessary costs of completing the
contract themselves. The defendants
at no time sought an extension of the time
for practical completion.
12. Finally on 12 April 2006, the
claimant’s solicitors wrote to the defendants as follows:
"Re: Notice of Termination of Building Contract: For Family JONES
1. We act for Mr. & Mrs. Jones in the above matter.
2. We are instructed the delay of the completion of our clients building is long overdue and amounts to a serious breach of the contract.
3. As of this date our clients are terminating their contract with San Construction and is suing you for liquidated damages".
There is no evidence that before that, the claimant gave
notice in terms of Clause 23. However, it is clear that the defendants accepted
the letter as termination of the contract. They did not protest about it or ever
indicate a wish or an intention to continue work.
Nor have they provided any
valid reason for ceasing to work at the site from about the start of
2006.
13. Mr. Feast carried out an inspection of the site as at 12 April
2006 and produced a list of the work required before a certificate
of practical
completion could be issued. It was extensive. Mr. Bue who is a qualified
engineer, has costed that work (apart from
electrical) at VT7,081,500. His
assessment is detailed and professional and was unchallenged. I accept it. Mr.
Boudier costed the
electrical work required to complete at VT803,650. Again his
evidence is unchallenged and I accept
it.
Discussion
14. I
am satisfied that by the date of termination, the defendants were well and truly
in breach of their contract. They had failed
to complete by practical completion
date without any contractual justification. They had failed to comply with the
obligation in
Clause 6 to regularly and diligently proceed with the works. I am
satisfied that by that time, there was no intention by the defendants
to resume
work at the site. Virtually everything owing to them to date had been paid to
them or to their creditors on the contract.
Their position at the time, as they
must have known, was that there was VT1,680,000 left on the contract price but
work to the value
of approximately VT8,000,000 to be carried out. Although it
was the claimant who formally terminated the contract, I am satisfied
that the
defendants had by then effectively repudiated it. On that basis, the
claimant’s letter of termination can be seen
as an acceptance of an
earlier repudiation. If I am wrong in that view, I hold that by their lengthy
absence from the site, and their
acceptance without protest of the termination
letter, the defendants waived the requirement of 14 days notice. So I am
satisfied
that one way or the other, the contract was validly terminated on 12
April 2006 by reason of the defendant’s breach of it.
It follows that the
claimant is entitled to recover the additional cost of completion.
15. As to the amount to complete, I am satisfied it has been properly
proven. Therefore the claimant is entitled to damages under
this head as
follows:
|
Amount to
complete
|
|
|
|
Building work
|
7,081,500
|
|
|
Electrical work
|
803,650
|
|
|
|
7,885,150
|
7,885,150
|
|
Less Balance due under Contract
|
|
1,680,433
|
|
|
|
VT
6, 204,717
|
16. As to the claim for liquidated damages for
non-completion, there is no certificate in writing from the architect that in
his opinion
the same ought reasonably to have been completed by practical
completion date. This cannot simply be presumed in the circumstances
where there
is no evidence that the architect had given any notice to the contractor that
liquidated damages were accruing. I am
therefore not prepared to award
liquidated
damages.
Conclusion
17. There
will be judgment for the claimant against the defendants in the sum of VT6,
204,717 together with interest at 5% per annum
since the date of filing of the
proceeding and costs to be agreed or fixed upon application made within 30 days.
There will also
be judgment for the claimant on the defendant’s
counterclaim. The defendants have been paid or credited with everything they
are
entitled to under the contract.
Dated
at Port Vila, this 21st day of May,
2008
BY THE
COURT
C.N.
TUOHY
Judge
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback|
Report an error
URL: http://www.paclii.org/vu/cases/VUSC/2008/20.html