![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
[Report an error]
[F.A.Q.]
Supreme Court of Vanuatu |
[Recent Decisions] [Noteup] [Download] [Help]
IN
THE SUPREME
COURT
OF THE
REPUBLIC OF VANUATU
(Civil
Jurisdiction)
Civil Case No. 140
of
1998
BETWEEN:
CAPTAIN
PAUL A.J.
MAKIN
Plaintiff
AND:
I.A.C.
PACIFIC LIMITED
Defendant
JUDGMENT
The plaintiff is a commercial airline pilot. The defendant is a company that seeks and contracts with airline pilots for them to fly for airlines, in this case Korean Airlines (KAL).
On 25 February 1996 the
plaintiff and defendant signed an agreement. At the commencement of the trial
there were claims for money
in respect of six specific issues arising out of the
contract:-
1. Failure of the defendant to pay the plaintiff the monthly good faith payment.
2. The “nine clear days off in Australia” dispute.
3. The training period levy underpayment.
4. The 13th month 5 year incident – free payment.
5. Taxation rebate losses.
6. Interest on late payment of salary.
I
will deal with each issue in turn. There are some general comments to be made
first.
This case came before the
Court of Appeal on
30th
October 2001, judgment was given on
1st
November, (Civil Appeal Case 14 of 2001). At page 6, paragraph 5 the Court of
Appeal stated:-
“It seems that both parties to these proceedings are intent on taking every technical point...The tactics which both parties are adopting, presumably in an effort to complicate and frustrate the aims of the other will serve merely to delay the inevitable and cause each party additional expense in the meantime.”
That
state of affairs has continued. Further, when deciding matters of costs and
taxation extra time will inevitably have to be spent
as a result of
this.
These tactics mean a disproportionate amount of Court time and resources are used on a case and taken from other cases. The new Civil Procedure Rules are now in force. The overriding objective of the Rules forbids such practices. There are costs sanctions.
There are three International
Air Crewing Companies, IAC Pacific, which contracted with the plaintiff, IAC
Australia which is described
as the defendant’s management agent and IAC
Korea which contracted with
KAL.
The plaintiff and defendant
called one witness each, respectively the plaintiff himself and Philip Jarvis.
Evidence in chief was given
by way of adoption of affidavits followed by cross-
examination and
re-examination.
The decisions upon
the issues finally remaining in dispute depend to a significant degree upon the
credibility and reliability of
those two
witnesses.
The plaintiff alleges
an “intentional misrepresentation” by the defendant through Paul
Moxham concerning the reduction
to be made in salary during the training period.
He says when first talking to IAC Pacific he understood there was an agreement
with
KAL, but later he began to suspect these wasn’t such a contract. When
formally put to Mr. Jarvis the latter replied there was.
The plaintiff then said
“From what I subsequently learned I doubt whether that was correct”.
He said as far as he was
concerned “9 days off” meant “9 day
complete days at home, namely Sydney”. That in reality turned out not
to
be correct. The 9 days started from completion of duty in Seoul. He said the
“13th
month, 5 years incident free payment” disappeared between initial
discussions and contract.
Mr.
Makin said a US$ 569 monthly good faith payment was withdrawn without any basis
in law or merit. Taxation rebates were not returned
promptly and late payment of
salary caused him interest and fee
charges.
In cross-examination it
was put to Mr. Makin that some of his answers were deliberately untrue, he would
say things to harm IAC and
that he had strong animosity towards Mr. Jarvis and
IAC. He was questioned about his career and prospects in the years before
joining
IAC Pacific. It was put that he jumped at the terms on offer and
regarded the job, with renewal, as seeing him through to retirement.
It was
suggested he was advised to consult a lawyer, this was rejected, and signed a
contract knowing what he was doing. Mr. Makin
stated that in certain documents
when he complimented Mr. Jarvis for improving his conditions and that of other
pilots that he was
being sarcastic and insincere. He agreed he had written to
the International Labour Organisation, the Australian Government and other
bodies about IAC and had placed an advertisement in the industry magazine Flight
International, which bore the name of the Vanuatu
Commissioner of Labour. It was
suggested that was defamatory of
IAC.
Mr. Jarvis gave evidence that
it was clear what was fixed and what was being negotiated. He says, as with all
prospective pilots,
he advised Mr. Makin to seek legal advice. He said the
contract was a matter for Mr. Makin if he wished to sign it. There were no
misrepresentations or attempts to mislead. Mr. Jarvis said he had worked hard to
bring about the improvements Mr. Makin said were
or should be in the contract
and had indeed achieved them by negotiation with KAL. He said, in essence, Mr.
Makin had been difficult
to deal with. He had far more correspondence with him
than any other pilot, and at times he had been insulting.
Whilst I do not reject the
evidence of Mr. Makin, where it differs from that of Mr. Jarvis, I prefer the
evidence of Mr. Jarvis. There
is the real risk that Mr. Makin’s
recollection of conversations several years ago is coloured by his feelings
towards Mr. Jarvis
and IAC. I do find that, whilst not desperate, he was eager
to sign up with IAC given his salary levels, actual work and prospects
over the
immediately preceding years. I accept it has not always been easy for IAC to
deal with Mr. Makin. However, lack of clarity
in the original contract document
together with IAC’s reactions to dealing with Mr. Makin have led to some
of the problems
in this case. The tactics employed in these proceedings are the
responsibility of both
parties.
There were areas in the
original contract of 1996 which were not as clear as they could be. It is
probable that as a result of the
initial discussion phases Mr. Makin came to
expect more than was in the contract. However, he did sign the contract. He is
an intelligent,
mature person, not a youthful or naïve
one.
I will deal with each issue
in turn and in doing so will further refer to matters of credibility and
reliability. I will take first
those that can be addressed
quickly.
4.
The 13 month – 5 year Incident – Free
Payment
Just before the
plaintiff’s case was opened this claim was abandoned, without notice. It
is, in money terms, the biggest of
the claims, greater then all the others put
together.
The defendant has been
awarded costs on this Part of the claim.
5
– 6. Taxation Rebate Loss – Interest on late Payment of
Salary
These two claims were
conceded by the defendant at the outset. They are respectively for the sums of
US$238.93 and US$18.19.
1. Failure of the defendant to pay the Plaintiff the Monthly Good Faith Payment
On
25th
February 1996 the plaintiff signed the contract with IAC Pacific,
(see pp. 17 –
29, Plaintiff’s Bundle). As a
result of correspondence and disagreements IAC Pacific wrote on
23rd
April 1997 to the plaintiff stating,
“Your inability
to be a team player when coupled with your breaches of Clause 5 (b) ... have
resulted in you leaving IAC Pacific no
alternative but to terminate the
Agreement.”
On
2nd
May Mr. Makin replied stated he wanted to continue his flying career with KAL
and acknowledging that
“IAC Pacific
Ltd has honoured my contract in the spirit and to the letter at all
times.” There were expressions of
regret and apology. Mr. Makin referred to the future execution of a deed to
reinstate the contract,
strict obedience to its terms and an undertaking not to
“commence any
proceedings against any officer or member of the IAC group of
companies.” He agreed a copy of the
letter could go to KAL, (exhibit L, affidavit of Mr. Jarvis). This was faxed to
IAC.
Jim Morris, Director of
Marketing and Strategic planning for IAC Pacific replied on
2nd
May accepting the apology and relying upon the assurances given. A deed was to
be drawn up. On the understanding Mr. Makin would
sign the Deed, the termination
notice would be withdrawn.
The
letter concluded,
“Finally, as
with other MD-80 Captains, effective from 1 April 1997 your gross salary payment
under your contract will be US$7,800
per month with the increase in the monthly
payment comprising flow on from the CPI increase of 3.3% provided for under the
contract
which IAC Pacific has with KAL and an additional amount which has been
provided as an act of good faith by IAC Pacific. The new monthly
salary will
apply up to and including payment for March
1998.” (Annex M, affidavit of Mr.
Jarvis).
On
28th
May 1997 the Deed of Settlement was signed, (Annex N). The Deed acknowledged the
original agreement, the termination of contract
and denial of any breach, the
discussions and affirmation to continue the agreement, the withdrawal of the
termination notice and
the undertaking by Mr. Makin to observe strictly and
perform the terms of the Agreement.
Mr. Makin covenanted to
“not engage in
any common talk or mischievous
activity” and only discuss matters
with IAC Pacific and its staff. There was a whole agreement clause and a mutual
release from claims
and suits.
Mr. Makin recommenced working for
IAC and flying for KAL. In August 1997 a dispute arose about sick leave Mr.
Makin intended to take
off for an exploratory operation, the provision of a
doctor’s report and the position vis à vis KAL.
On
14th
August Mr. Morris wrote to Mr. Makin setting out the company’s position,
(Annex O). The letter concluded
“Should you
fail to cooperate in the manner referred to above you are on notice that from 01
September 1997 the gratuity payment of
US$569 per month will
cease.”
By a further letter of
19th
September the additional amount of US$569
“by way of a
gratuity ... included in the new monthly salary ‘as an act of good
faith’ over and above the contracted
rate” was withdrawn. No reason was
given in the letter for this. Mr. Jarvis in his affidavit (paragraph 31) states
this was done
as the
“Plaintiff had
failed to furnish the defendant with a medical
certificate.”
The plaintiff says that sum of
$569 had become part of the salary package in the contract. It could not be
unilaterally withdrawn
in that way. The defendant argued it was a discretionary,
good faith payment. There was no contractual obligation to pay it. In any
event,
there was no consideration for such an increase in the plaintiff’s salary.
Mr. Jarvis stated in evidence that he did
not know why the word
“gratuity”
was used after payment began. As a layman he saw no distinction between an
“act of good
faith” and a
“gratuity”,
to the company there was no distinction. The next salary review would be
1st
April 1998.
To resolve this
question the circumstances pertaining in May 1997 must be considered.
The letter of
2nd
May states, “as
with other MD-80 Captains ... your gross salary payment under your contract will
be US$7,800 per month.” The extra
$569 was not peculiar to Mr. Makin. It was being paid to all captains. It was to
be part of the
“gross salary
payment”. The extra was provided
“as an act of
good faith.” There is no evidence,
it was stipulated as being: discretionary, ‘at the discretion of
management; with ‘no contractual
obligation’; ‘contingent upon
good behaviour’ or subject to ‘satisfactory performance’. No
statement
was made other than it being an increase in salary as an act of good
faith by IAC. The letter concluded by calling the total sum
“the new
monthly salary”.
The Deed of Settlement stated IAC
had terminated Mr. Makin’s contract. Mr. Makin denied the breach. Thus,
immediately before
the Deed was signed there was no contract between the
plaintiff and defendant. There was a dispute over the termination of the
contract
of
25th
February 1996. There was the real potential for legal proceedings between the
parties. No mention was made of the $569 in the Deed.
In my judgment the Deed was a new
agreement which incorporated the original contract and all its terms but with
the variation that
the monthly salary was then $7,800 per month, the parties
agreed to forego any suits they may have had in relation to the termination,
a
whole agreement term was added to the original agreement and Mr. Makin agreed to
proscribe his activities in certain ways more
comprehensively than before,
(Clause 2.2 and 2.3).
The first
reference to the sum being
“ex-gratia”
or
“gratuitious”,
on the evidence, is in the letter of
14th
August. That letter states
“It is
essential part of our relationship that at all times you co-operate in order to
assist us in our dealings with KAL. In recognition
of this co-operation
ex-gratia or gratuitous amounts are extended to pilots from time to
time.
“Should
you fail to co-operate ... you are on notice that from 01 September 1997 the
gratuity payment of US$569 per month will
cease.”
The letter of
19th
September said the
“$569 by way of
gratuity was included in the new monthly salary ‘as an act of good
faith’ over and above the contracted
rate.” Notice was given to Mr.
Makin it was being withdrawn.
I
find the $569 was not an amount payable or with holdable at the discretion of
the defendant. It was part of Mr. Makin’s
“new monthly
salary”. IAC could not withdraw
payment of it for the reasons they did. The money was described as being
provided in good faith and
together with the original salary and CPI increase of
3.3% formed
“the new
monthly salary”. This is to be
compared for example with the discretionary Christmas bonus of $100, (see P 56
Bundle, Letter
18th
December 1996).
The defendants
argue that, if successful, the claim under this head should be limited to the
six months from time of withdrawal to
March 1998. Interest should be at 5%, not
the 9.75% claimed by the plaintiff.
The plaintiff claims the sum for
the period until the contract was ended. That is a total of 35 months, the
amount apparently varied
for the periods in question. Interest was claimed at
9.75%.
Little evidence or
argument was directed to this particular point.
The amended statement of claim
seeks the sum of US$19,721 plus interest, that is for the period October 1997 to
August 2000 when the
contract finished. (See Schedule A to the claim. Schedule A
alleges slight variations in the figure of $569, both down and up.) There
is a
blanket denial in defence.
There
is no specific evidence as to when the contract signed on
25th
February 1996 actually came to an end. According to its terms (paragraph 2) it
was to run for five years; that was affirmed in the
Deed of Settlement. The
claim is limited to the period up to August
2000.
In the contract under
Section 8 Payment there is paragraph
‘h’
which is entitled
“Annual
review” –
“It is agreed
that the total remuneration due to captains as well as other terms and
conditions of this Agreement shall be reviewed
on an annual
basis.”
The new salary including the $569
applied “up to
and including payment for March
1998”. By his letter of
19th
September 1997 (p. 152) Mr. Morris purported to withdraw the payment from
1st
September 1997. He continued
“IAC will
assess your cooperation with IAC on a yearly basis from September 01 to
September 01 each year for the term of the contract.
Therefore on September 01,
1998 IAC may make retrospective monthly payments of goodwill should we believe
it to be warranted”.
There is no evidence what, if
any, review took place. There is no evidence as to what happened concerning this
payment in respect
of other captains. Mr. Makin in correspondence did not accept
the reduction.
In January –
February 1998, as a result of the Asian economic crisis KAL sought reductions in
payment to IAC in respect of their
pilots. Mr. Makin accepted a reduction of 5%
by an agreement dated
8th
February 1998. Paragraph 3 states
“The parties
also agree that notwithstanding the effects of clause 1.1 (the 5% reduction
clause) and 1.2 of this agreement the entitlement
due to the captain shall be
not less than US$7,410 per month.”
The figure $7,410 is $7,800 less
5%. There is no mention of a review or other circumstances peculiar to Mr.
Makin.
Accordingly in my judgment
the sum of $569 was withheld from Mr. Makin’s salary. There was no legal
basis for that withholding.
The term of the contract was till
27th
February 2001. The actual claim is to August 2000. There is no evidence Mr.
Makin agreed to the withholding of that sum when first
occasioned or at any
subsequent review. There is no evidence the sum was varied save for the 5%
reduction in February 1998. There
is no evidence as to when salary levels were
restored or the 5% reduction removed.
In the circumstances I find, on
the balance of probabilities, that Mr. Makin is entitled to $569 for the months
October 1997 to February
1998, that is 5 x $569 = $2,845, together with 30
months (March 1998 to August 2000) at $540.55 per month ($569 less 5%) =
$16,216.50,
a total of $19,061.50.
2. The “nine clear days off in Australia” Term
The plaintiff lives in
Adelaide, Australia. KAL operate out of Seoul in Korea. According to the
contract, Clause 15 (a)
“MD-82 Captains
shall have nine (9) days off per month after twenty-one (21) consecutive days
actual duty per month. Commuting time
to and from his home shall not be included
in the 21 actual duty per month”.
Mr. Makin says nine days off
means nine clear days starting at 0001 hours on the day after his arrival in the
country of his residence.
In reality this would be Sydney. Travel to Adelaide,
his home, is a matter for him. It ends at 23.59 on the day before his departure
from Sydney to return to duty. He says this arrangement is common for aircrew of
international airlines.
Mr. Makin
states when travelling back to Sydney he is required to travel in uniform, and
may be called upon to assist, which occasionally
has happened.
Further, the letter of Mr. Jarvis
dated
18th
January 1996 (Annex B) states
“Base: Anywhere
on the Korean network”. Sydney is
on the Korean network.
The
defendants deny this. They say in the conversations before the contract was made
there was no reference to
“in
Australia”. They accept
“nine
clear
days” was referred to, (letter of
Philip Jarvis to Capt. Douglas,
18th
January 1996). This is a matter of credibility. The evidence of Mr. Jarvis is
preferred.
Further, Mr. Makin was
advised to seek legal advice. The contract itself although not entirely clear in
its terms, nowhere states
“in
Australia” and the main impact is
that off duty starts in Seoul. There is reference to a “Flight Base”
of Los Angeles in
the contract. This is artificial as most captains, including
the plaintiff, would not go there before going home for off-duty periods.
‘Per diems’ are paid in respect of this, in effect a perk which
cannot reasonably drawn as well as having a Flight Base
of Sydney.
Reference is also made in Capt.
Moxham’s letter of
18th
February 1996 (Annex E, Jarvis affidavit) to
“... and we
have managed to increase the MD-82 days free of duty per month, based on a
balance of 21 days duty Seoul for the MD-82
with no soft days
...”
The defendants further argue by
the Deed of Settlement executed on
28th
May 1997 the defendant is estopped from going outside the terms of the contract.
This issue has already been
resolved between KAL, IAC and the captains. Mr. Makin’s flight base is now
defined as Sydney. His
claim is for payment in respect of the days he should
have had free of duty, but didn’t.
There is much correspondence
before me on this topic. That correspondence includes argument as to how the two
different calculations
of the nine days off would and could work in practice. I
need not enter into that debate.
First, Mr. Makin signed the
original contract of
25th
February 1996. I have stated I prefer the evidence of Mr. Jarvis. In this
context this specifically relates to the urging of all
captains to obtain legal
advice. Mr. Makin chose to sign the contract, whether he did so with or without
advice, or even reading
it properly, (see for example paragraph 15 (c) of his
affidavit) was a matter for him.
Mr. Makin signed the Deed of
Settlement on
28th
May 1997. Again whether or not that was with advice or a proper reading of the
Deed, was a matter for him. That Deed, as I have found,
constituted a new
agreement. Clause 1 reinstated the February 1996 agreement as though it had not
been in terminated. Clause 3 states
that
“The Parties
hereby acknowledge and agree that the terms and conditions contained in the
Agreement comprise the actual terms of the
contractual relationship ... and that
no other terms or conditions apply to or form part of the Agreement save and
except such terms
and conditions as may be implied or incorporated under the
laws applicable to the Republic of Vanuatu (excluding French
Law).
I therefore look to the contract
for the resolution of this dispute. That states clearly the flight base is Los
Angeles, (Clause 10).
Per diems are paid when a captain is away from his flight
base, (Clause 11).
Clause 15 (a)
does not fully cover the question. It is clear that twenty-one days consecutive
duty has to be worked per month. Nine
days off per month are granted. This, of
course, must be calculated over a year, not calendar month by calendar month.
Commuting
to and from home is not included in the twenty-one days duty.
It might be suggested the nine
days did not start in Sydney, as Mr. Jarvis had to negotiate to get that for
KAL. However, that is
between KAL and IAC Korea, it is not a matter between IAC
Pacific and Mr. Makin.
If the
pre-contract letters and conversations are examined there is no reference to
‘in Australia’ for the nine days off.
There is in the
18th
January 1996 letter reference to “Base: Anywhere on the Korean
Network”. The contract states “Flight Base: Los
Angeles”,
however artificial that might be.
If Mr. Makin started his nine
days off in Los Angeles then it is likely he would end up with the same or even
fewer clear days off
in Australia.
There is an argument that the
parole evidence would support a flight base of Sydney, a destination on the
Korean Network. The response
is that parole evidence should not be admitted. The
contract terms are clear.
The
onus of proof is on the plaintiff on the balance of probabilities to establish
his claim. That requires him to show his flight
base, or place where his days
off commence is Sydney. I find that on this issue he has failed to do that. I
dismiss it. (D4 –
Letter of
7th
November).
3. The Training Period Levy Underpayment
There is a training period
before Captains take up their duties with KAL. For that period they are paid a
reduced salary. Mr. Makin
alleges he was told the reduction made by KAL to IAC
in this respect was $2,000 per month. In fact there was no reduction and for
the
period of his training he was underpaid a total
$5,372.
The discovery by the
defendant of the contract between KAL and IAC Korea showed for his class of
captain the reduction was $1,500.
The claim was modified to $500 per month for
three months. It was alleged there was an intentional misrepresentation by Mr.
Moxham
of IAC. He has not given
evidence.
The defendants replied
that if one looks at the figures for the captains of the various category of
aircraft the rough average is,
indeed, a reduction of $2,000 per month. Some are
more, some including MD-82 captains are
less.
It was put to the plaintiff,
“what Moxham
said concerning the training salary was the
truth.” The answer was
“Yes”.
“There was no
misrepresentation on amount, the fact is there was a
reduction”.
“No. The
question is not what came out in the contract. He implied the differential was
$2,000.” Mr. Makin did not wish to
withdraw the claim.
The defendants
say this exchange clearly illustrates the mentality of the
plaintiff.
There is the Deed of
Settlement. The contract clearly states (Clause 8 (a))
“Base Salary
during training. Base salary shall be US$3,000 per calendar month, less taxed
deducted under Clause 19”. That sum
per month has been paid.
Early
disclosure of sufficient of the KAL – IAC Korea contract to show the
relevant figures might have resolved this issue at
a much earlier stage.
However, I find the plaintiff has failed to prove his claim on this issue. It is
dismissed.
Accordingly I give
judgment as follows:-
1. Judgment is entered for the plaintiff in the sum of US$19,061.50 in respect of the monthly good faith payment together with interest at 5% per annum.
2. The claim in respect of the “nine clear days off” in Australia is dismissed.
3. The claim in respect of the “training period levy underpayment” is dismissed.
4. Judgment is given for the plaintiff in respect of the Taxation rebate losses in the sum of US$238.93 together with interest at 5% per annum.
5. Judgment is given for the plaintiff in respect of the “reference fee” of US$18.19 plus interest at 5% per annum.
For the avoidance of
further dispute the rate of interest of 5% per annum is awarded with yearly
rests upon
1st
March until payment. The selection of the figure of 5% is made without specific
evidence upon what is an appropriate rate of evidence.
To hear such evidence
would be wholly out of proportion to the difference
involved.
I will hear the parties
on costs.
Dated
at Port Vila, this ..... day of February 2003.
R. J. COVENTRY
Judge
PacLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback|
Report an error
URL: http://www.paclii.org/vu/cases/VUSC/2003/7.html